State Highway 59, the Hill Highway, at Elappara, April 2023. Arunvrparavur · CC BY-SA 4.0 · Resized for display.
A multi-package road programme; completed packages and the programme as a whole are different units.
Hill Highway projects: completed and ongoing
On 31 March 2025, five of 47 KIIFB-funded Hill Highway projects were completed and 42 ongoing. These project counts do not describe completion of the entire highway.
+
The report lists 47 KIIFB-funded Hill Highway projects: five completed and 42 ongoing as of 31 March 2025.
The government reports 473.42 km completed of a 1,179.45-km Hill Highway, with 793.68 km separately described as under KIIFB development. The lengths may overlap.
+
The report describes a Hill Highway of 1,179.45 km, with 473.42 km completed. It separately says 793.68 km is being developed under KIIFB.
Project counts, completed kilometres and the full highway’s length are different measures. Completed packages represent partial progress across the wider route.