The report records commissioning in July 2020 and 12,684 hectares irrigated at commissioning. Cumulative expenditure of Rs 1,153 crore covers the long-running project, whose construction began in 1974.
Muvattupuzha Valley project commissioning
In brief
Commissioned in July 2020, the Muvattupuzha Valley project irrigated 12,684 hectares at that stage. Its ₹1,153 crore cumulative cost covers the long-running project begun in 1974.